Bor - Malakal Power Transmission Line
Overview
Summary
Located between the city of Bor and Malakal. Implementation of a transmission line from Bor to Malakal. This is a step for the transmission line from Juba to Malakal, which aim is to transfer energy from the south (hydropower production and interconnection with Uganda, Kenya and Ethiopia) to the north of South Sudan (interconnection with Sudan and Ethiopia) and develop National grid. 400/500 kV of length of 366km
Estimated cost is USD 108 million.
Description
Located between the city of Bor and Malakal. Implementation of a transmission line from Bor to Malakal. This is a step for the transmission line from Juba to Malakal, which aim is to transfer energy from the south (hydropower production and interconnection with Uganda, Kenya and Ethiopia) to the north of South Sudan (interconnection with Sudan and Ethiopia) and develop National grid. 400/500 kV of length of 366km
Estimated cost is USD 108 million.
Objectives
Progress history
- 2022 Project Definition planned: Feasibility
Key facts
- Status
- Active
- Countries
- South Sudan, South Sudan
- Last updated
- 22 Apr 2022
Financing
USD million- Preparation cost
- 0.00
- Preparation funding gap
- 0.00
- Capital cost (CAPEX)
- 108.00
- CAPEX funding gap
- 0.00
- Operation cost
- 0.00
Stakeholders
- Nile River Basin Program
- NRBIP
- Government of South Sudan
- GoSS