Kinyeti Hydropower Project

Energy Hydro Power Plant

Overview

Summary

Kinyeti HPP, located on its namesake river, will consist of a diversion weir with accompanying sluiceway and head regulator, transiting the river"™s discharge via a 500 m long channel culminating in a bypass pipe and penstock. The penstock will then transit the discharge to the powerhouse which will be equipped with three (3) Pelton units for an installed capacity of 1.95 MW. Geographic Coordinates: 4° 1' 34" N, 32° 49' 7" E. The plant will have 3 units, Design Discharge 2.1 m3 /s, Reservoir FSL 1 272 m, Reservoir MOL 1 272 m, Total Installed Capacity 1.95 MW (3 x 0.65 MW), Firm Energy 5.8 GWh and Average Energy 9.6 GWh. The Project Costs (excl. Transmission Lines) 14.03 US$ M

Description

The Kinyeti Hydropower project is a planned renewable energy project on the Kinyeti River, South Sudan. It aims to generate clean electricity for the region by harnessing the river’s discharge and head. The project also considers environmental and social impacts and aligns with South Sudan’s energy access goals.

Progress history

  • 2022 Project Definition planned: Feasibility

Key figures

Dimension Planned Achieved
Number of Units 3 units 0 units
Power 2 MW 0 MW

Key facts

Status
Active
Countries
South Sudan, South Sudan, South Sudan
Last updated
21 Apr 2022

Financing

USD million
Preparation cost
0.00
Preparation funding gap
0.00
Capital cost (CAPEX)
14.00
CAPEX funding gap
14.00
Operation cost
0.00

Stakeholders

Nile River Basin Program
NRBIP
Government of South Sudan
GoSS

Source: African Infrastructure Database (AUDA-NEPAD)