Ngono Valley Multipurpose Water Resource Development Project aims to boost national and regional economic development through The prefeasibility and diagnostic studies of the project were completed in 2012 under NELSAP while the feasibility studies and preparation of detailed designs is underway with funding from WB/CIWA.
Description
Ngono Valley Multipurpose Water Resource Development Project aims to boost national and regional economic development through The prefeasibility and diagnostic studies of the project were completed in 2012 under NELSAP while the feasibility studies and preparation of detailed designs is underway with funding from WB/CIWA.
Objectives
irrigation development of 13,000 ha, 26m earthfill dam (Kalebe Dam) across the Ngono East River.
The project will help to reclaim 7,000 ha that are currently swampy due to flooding and poor natural drainage in the Ngono valley, and will also allow
for restoration of critically degraded 'hotspots"' in the 3,200 km2 catchment upstream of the proposed dam.
Progress history
- 2020 Feasibility planned: Project Structuring
Key facts
- Status
- Active
- Countries
- Tanzania, Tanzania, Tanzania
- Last updated
- 25 Apr 2022
Financing
USD million- Preparation cost
- 0.00
- Preparation funding gap
- 0.00
- Capital cost (CAPEX)
- 172.00
- CAPEX funding gap
- 97.00
- Operation cost
- 0.00
Stakeholders
- Nile River Basin Program
- NRBIP
- Tanzania - Government of Tanzania
- GoTZ