Kinyeti River Multi-purpose Water Resources Development Project

BIP_ENTRO_009 Water Multi-purpose Reservoir

Overview

Summary

Kinyeti River has its origins in the Imatong Mountains close to the South Sudan-Uganda border and from there flows northwards, eventually dispersing into the Badigeru swamp. The proposed project has multiple components including small scale potable water supplies, fisheries management, irrigation, livestock watering and watershed management.

The Kinyeti River multipurpose development project is one of the three short term projects proposed as part of the Baro-Akobo-Sobat multipurpose water resources development study project. The three short term projects are based on the sustainable development of water resources. They aim at providing inter-sectoral benefits and improving peoples livelihoods in the sub-basin. The Kinyeti project is centered around the construction of a multipurpose dam in Eastern Equatoria, South Sudan, upstream of the city of Torit.

The project has been designed to provide the following benefits:

The 45 million m3 reservoir will secure water access for the city of Torit (100,000 inhabitants projected in 2041). It will also support capture fisheries and recreational activities

The regulation of the flow will provide water for the development of irrigation (1,000 ha) and aquaculture (100 ponds of 200 m²) downstream of the dam. It will also provide water for the livestock all year round and satisfy an environmental flow during the dry season. Irrigation and aquaculture will be introduced in this area and there would be room for further expansion of these activities in the future.

Feasibility studies completed with an estimated investment costs is USD 92 million

Description

Kinyeti River has its origins in the Imatong Mountains close to the South Sudan-Uganda border and from there flows northwards, eventually dispersing into the Badigeru swamp. The proposed project has multiple components including small scale potable water supplies, fisheries management, irrigation, livestock watering and watershed management.

The Kinyeti River multipurpose development project is one of the three short term projects proposed as part of the Baro-Akobo-Sobat multipurpose water resources development study project. The three short term projects are based on the sustainable development of water resources. They aim at providing inter-sectoral benefits and improving people’s livelihoods in the sub-basin. The Kinyeti project is centered around the construction of a multipurpose dam in Eastern Equatoria, South Sudan, upstream of the city of Torit.

The project has been designed to provide the following benefits:

The 45 million m3 reservoir will secure water access for the city of Torit (100,000 inhabitants projected in 2041). It will also support capture fisheries and recreational activities

The regulation of the flow will provide water for the development of irrigation (1,000 ha) and aquaculture (100 ponds of 200 m²) downstream of the dam. It will also provide water for the livestock all year round and satisfy an environmental flow during the dry season. Irrigation and aquaculture will be introduced in this area and there would be room for further expansion of these activities in the future.

A Feasibility studies completed with an estimated investment costs is USD 92 million

Objectives

The project has been designed to provide the following benefits:

The 45 million m3 reservoir will secure water access for the city of Torit (100,000 inhabitants projected in 2041). It will also support capture fisheries and recreational activities

The regulation of the flow will provide water for the development of irrigation (1,000 ha) and aquaculture (100 ponds of 200 m²) downstream of the dam. It will also provide water for the livestock all year round and satisfy an environmental flow during the dry season. Irrigation and aquaculture will be introduced in this area and there would be room for further expansion of these activities in the future.

Economics

Th economic indicators are available for each component in the visibility study 

Progress history

  • 2024 Feasibility
  • 2020 Pre-Feasibility planned: Feasibility

Key figures

Dimension Planned Achieved
Annual Hydroelectric Production 8 GWh 0 GWh
Area equipped for irrigation (ha) 1,000 ha 0 ha
Area of watershed under improved management 70,700 ha 0 ha
Direct Beneficiaries - catchment management 225,000 persons 0 persons
Direct Beneficiaries - household water supply 100,000 persons 0 persons
Total Installed Capacity 3 MW 0 MW

Key facts

Programme
Eastern Nile Technical Regional Office (ENTRO)
Status
Active
Countries
South Sudan, South Sudan, South Sudan
Region
East Africa
Last updated
25 Sep 2026

Financing

USD million
Preparation cost
0.00
Preparation funding gap
0.00
Capital cost (CAPEX)
106.40
CAPEX funding gap
0.00
Operation cost
0.00
Total cost
106,400,093.34