← Back to all projects

Titsi Irrigation Development and Watershed Management Project Nile Equatorial Lake Subsidiary Action Programme (NELSAP-CU)

Water Agricultural irrigation and drainage

Overview

Summary

This project, located in Cheptais Sub-Country, Bungoma County, Western Kenya was identified under the Sio-Malaba-Malakisi River Basin Project. Project interventions include construction of a water intake on the Titsi River (tributaries of the Lwakhakha River), laying 5.8 km of pipeline for water conveyance; and development of an irrigation command area of 1,356 ha. The project will also include provision of drinking water supply; provision of water for livestock; development of fish ponds and watershed management. It is expected to benefit 3,345 people.coordinate UTM 36 N 0661577 E 0092214.

Description

This project, located in Cheptais Sub-Country, Bungoma County, Western Kenya was identified under the Sio-Malaba-Malakisi River Basin Project. Project interventions include construction of a water intake on the Titsi River (tributaries of the Lwakhakha River), laying 5.8 km of pipeline for water conveyance; and development of an irrigation command area of 1,356 ha. The project will also include provision of drinking water supply; provision of water for livestock; development of fish ponds and watershed management. It is expected to benefit 3,345 people.coordinate UTM 36 N 0661577 E 0092214.


Progress history

  • 2022 Project Definition planned: Feasibility

Key figures

Dimension Planned Achieved
Area equipped for irrigation (ha) 1 ha 0 ha
Direct Beneficiaries - irrigation 3 persons 0 persons

Key facts

Status
Active
Countries
Kenya, Kenya, Kenya
Last updated
20 Apr 2022

Financing

USD million
Preparation cost
2.00
Preparation funding gap
0.00
Capital cost (CAPEX)
15.00
CAPEX funding gap
0.00
Operation cost
0.00

Stakeholders

Nile River Basin Program
NRBIP
Kenya - Government of Kenya
GoKE

Source: African Infrastructure Database (AUDA-NEPAD)