← Back to all projects
Mushangubo Multipurpose Water resources development project
Water Multi-purpose Reservoir
Overview
Summary
Project is located in Western Kenya and was identified and prepared under the Mara River Basin Project. Project interventions include A 35m high dam would store a volume of about 210 Mm3 and inundate an area of 15km2. Installed capacity is 5.47 MW. Size of land irrigated is 4000 ha. Investment costs is US$ 468.8 millions
Description
A 35m high dam would store a volume of about 210 Mm3 and inundate an area of 15km2. Installed capacity is 5.47 MW. Size of land of 4,000ha.
Progress history
- 2020 Feasibility
Key facts
- Status
- Active
- Countries
- Kenya, Kenya, Kenya
- Last updated
- 20 Apr 2022
Financing
USD million- Preparation cost
- 0.00
- Preparation funding gap
- 0.00
- Capital cost (CAPEX)
- 468.80
- CAPEX funding gap
- 469.00
- Operation cost
- 0.00
Stakeholders
- Nile River Basin Program
- NRBIP
- Kenya - Government of Kenya
- GoKE