← Back to all projects

Ruvyironza Multipurpose Water Resources Development Project

Water Multi-purpose Reservoir

Overview

Summary

Ruvyironza Multipurpose Water Resources Development Project is located along the Ruvyironza River (a tributary of the Kagera River) near the village of Gatake in central Burundi. The project is envisaged to include a 65 m height composite earth fill-concrete dam with storage capacity of 266 MCM, which will expand irrigation by 14,674 ha and provide food for about 124,740 people (paddy rice and likely to include pulses and vegetables for local markets including Gitega town). The project also includes hydropower generation of 22 MW, supply of power to 846,000 people, supply of drinking water to 265,000 people, and restoration of degraded lands in the 2000 km2 catchment upstream of the dam.

Description

Ruvyironza Multipurpose Water Resources Development Project is located along the Ruvyironza River (a tributary of the Kagera River) near the village of Gatake in central Burundi. The project is envisaged to include a 65 m height composite earth fill-concrete dam with storage capacity of 266 MCM, which will expand irrigation by 14,674 ha and provide food for about 124,740 people (paddy rice and likely to include pulses and vegetables for local markets including Gitega town). The project also includes hydropower generation of 22 MW, supply of power to 846,000 people, supply of drinking water to 265,000 people, and restoration of degraded lands in the 2000 km2 catchment upstream of the dam.

Identification/prefeasibility studies for the project were carried out by NELSAP-CU in 2012 with grant financing from the governments of Sweden and Norway. The project is in the NELSAP project pipeline awaiting funding for feasibility studies.

Progress history

  • 2020 Feasibility planned: Construction

Key figures

Dimension Planned Achieved
Area equipped for irrigation (ha) 14 ha 0 ha
Direct Beneficiaries - household water supply 265 persons 0 persons
Direct Beneficiaries - irrigation 124 persons 0 persons
Power 22 MW 0 MW
Storage Capacity 0 km3 0 km3

Key facts

Status
Active
Countries
Burundi, Rwanda, Burundi, Rwanda, Burundi, Rwanda
Last updated
20 Apr 2022

Financing

USD million
Preparation cost
0.00
Preparation funding gap
0.00
Capital cost (CAPEX)
268.00
CAPEX funding gap
268.00
Operation cost
0.00

Stakeholders

Nile River Basin Program
NRBIP
Burundi - Government of Burundi
GoBI
Rwanda - Government of Rwanda
GoRW

Source: African Infrastructure Database (AUDA-NEPAD)